Two stock guides. Read them in this order.
Guide 1 · You are here · Read firstHold less without running out

Sets how much of each item you should keep: a cushion, when to reorder, and the most you should hold.

→ Guide 2 · Read nextTurn idle stock back into cash

Deals with the stock above that level: finds it, gets cash back from it, and stops it building up again.

Why this order? You can only call stock “too much” once you know how much you should keep. This guide sets that level for each item; Guide 2 deals with everything above it.

01 · Introduction

Keep the protection, lose the guesswork

Most manufacturers hold extra stock because they have been caught short before: a late supplier, a line that stopped, a rush order. That protection is worth keeping. This guide helps you decide how much each item really needs, when to order again and how much to buy, so the extra is there on purpose and not out of habit.

Know what you use

Check what you have, what you use and how long suppliers take

Sort your items

More attention for costly, uneven and critical items

Estimate use

Simple methods, only where past use helps

Set levels

A cushion, a reorder point and an order size

Put it in place

Test on a few items first and watch for shortages

Why we hold extra, and what protects you instead
“Suppliers are late”→

Measure how long each supplier really takes, and plan for that

“A shortage stopped us once”→

Mark the items that can stop the line and give them a bigger cushion on purpose

“The bulk discount”→

Check the discount against what the extra costs to store and finance

“We might need it”→

Keep a set amount for a named reason, and check it every quarter

“Customers want it now”→

Keep finished goods for your busiest items, and ask customers what is coming

None of these reasons is wrong. Each is a real risk handled with a rough rule. This guide swaps the rough rule for a number you can explain for each item: how much you use, how long the supplier takes, how often you check and how much cushion you want. When someone asks why an item holds what it holds, the answer fits on one row of a spreadsheet.

What does your stock cost to hold?

Days of stock99
Cash tied up in each day of stock$9,589
Rough yearly cost of holding$133,000

Example manufacturer. The 6% for other costs is an example, and some costs, such as rent, do not fall when stock does. An estimate, not a saving.

You will need

  • Each item with the quantity on hand and what one unit costs
  • 12 months of use for each item; daily or weekly if you have it
  • Order and delivery dates for recent purchase orders
  • Supplier minimums, the production plan and parts lists

Our example manufacturer

A $5 million building-products maker with $950,000 of stock: $520,000 of materials, $130,000 in production and $300,000 of finished goods. All figures are examples.

If you do only three things

1Plan materials from the production plan

Not from last year’s use, for anything that goes into a known job.

2Check before you buy

Stock on hand, plus what is on order, minus what is promised to jobs. Every time.

3Set reorder points for busy items

Start with the simple method in section 05 and fine-tune later.

This guide covers the materials and finished goods you plan to keep. Clearing out excess, slow-moving and obsolete stock and stalled jobs is in the companion guide.

02 · Know what you use

Know what you have and what you use

Every number in this guide starts from two facts about each item: how much you have and how much you will use. Check the first, then work out the second. There are two kinds of use, and they are planned differently.

Use you estimate

Finished goods you sell from stock, spare parts and service items

From customer forecasts, firm orders and past sales
Use you calculate

Materials and parts that go into your products

1,200frames planned next month
×
4 kgaluminum per frame, from the parts list
=
4,800 kgaluminum needed
Figure 1. Estimate what customers buy; calculate what goes into it

For materials that go into known jobs, plan from the production schedule, not from last year’s use. Last year still includes orders that were cancelled or will not repeat. If you make to stock without a firm plan, estimate the finished goods first, then multiply through the parts list (often called the bill of materials).

Do the stock records add up?
Opening
+
Received
−
Used
−
Scrapped
=
Closing
Count check: of the items you count, how many match the system closely enough? If fewer than 95 in 100 match, fix the records before setting levels.Count costly items and items that can stop production every month, the rest at least once a year.

Then measure how long each supplier really takes. For the last ten or so deliveries, note the day you placed the order and the day the goods arrived. Write down the usual time and the longest. A quoted lead time is a promise; the dates on your receiving records are what your cushion has to cover.

03 · Sort your items

Give the most attention to the items that matter most

With a few hundred items, you cannot give each one the same attention. Sort them two ways, then add three flags that can change the rule.

Value: how much you spend on it in a year
Afirst 80%
Bnext 15%
C

Yearly use × unit cost, ranked from largest to smallest. The items that make up the first 80% of spending are A items.

Swing: how much monthly use jumps around
Lowunder 0.5
Medium0.5 to 1
Highover 1

A swing score the toolkit works out: the typical monthly jump divided by the average month. These cut-offs are starting points, not industry rules.

Seasonal

Use peaks in the same months every year.

Critical

Running out would stop production or a key customer’s order, with no approved substitute.

No use in 12 months

Check it in the companion guide before deciding anything.

Steel coil A · low swing

About 21 tons a month · swing score 0.08

Tempered glass panels B · high swing

About 18 panels a month, in lumps · swing score 1.26

Deck coating B · seasonal

Peaks April to August every year · swing score 0.78

Figure 2. Twelve months of use for three of the example manufacturer’s items
Low swing
Medium
High
No use in 12 months
A
20 items$190k
14 items$115k
8 items$85k
68 items$95kCheck in the companion guide
B
30 items$60k
25 items$55k
20 items$60k
C
60 items$35k
70 items$45k
105 items$80k
Watch closely: reorder points, smaller and more frequent orders Cushion plus customer forecasts Simple rules: bigger, less frequent orders Order only when a job needs it
Figure 3. The example manufacturer’s 420 materials and finished goods, by number of items and stock value

Sort materials and finished goods separately. Work in progress does not follow these rules; it depends on when you release jobs to the floor. Mark seasonal and critical items on top of their group: the example has 12 seasonal items and 9 critical ones.

Agree the critical list with the production lead, item by item, and keep it short. If everything is critical, nothing is. Mark seasonal items from two years of history if you have it, or from what sales and customers expect.

04 · Estimate use

Estimate future use simply, and only where it helps

You do not need forecasting software. Only forecast items whose past use is a good guide to the future. For everything else, use the production plan, customer forecasts and firm orders.

Steady items

Average of the last three months

(20 + 22 + 24) ÷ 3 = 22
Seasonal items

Same month last year, adjusted for this year

running 10% ahead? add 10%
Uneven items

Customer forecasts and firm orders

past use only as a check
New items

Best estimate from sales or the customer

review after 3 months
Materials for known jobs

Production plan × parts list

no forecast needed
26221814Tons a month JanFebMarAprMayJunJulAugSepOctNovDecNext
What was usedEstimate: average of the three months beforeNext month: 22 tons
Figure 4. Steel coil: a three-month average follows steady use closely
How far off?

Add up the misses, ignoring plus or minus, and divide by what you actually used

Do it in dollars across all A items for the month. The toolkit does it for you.

14%October: off by 14%
Too high or too low?

Add up estimate minus actual, keeping plus and minus, and divide by what you actually used

Above zero: you keep estimating high and building stock. Below zero: shortages become more likely.

+6%A little high
Figure 5. Two checks each month: how far off the estimate was, and in which direction

Check both every month for A items. If an item keeps missing by a lot, stop estimating it from history and plan it from customer forecasts and orders instead. If estimates run high three months in a row, ask who owns the estimate and what it assumed.

When a customer sends a forecast, write it next to your own estimate and compare both with what they actually ordered. After three months you will know whose numbers to trust.

05 · Safety stock

Safety stock: your cushion against surprises

Safety stock is the extra you keep in case you use more than usual or a delivery comes late. It lowers the chance of running out; it cannot remove it. There are two ways to set it. Start every item on the simple method, and move an item to the advanced method only once you have good records for it.

The simple method: plan for a busy spell during a slow delivery
A bad stretch

Your busiest day’s use × your slowest delivery

1.4 × 15 = 21 tons
−
A normal stretch

Your usual daily use × your usual delivery time

1.0 × 10 = 10 tons
=
Safety stock

The cushion that covers the difference

11 tons
Steel coil: the plant normally uses 1 ton a day and has used 1.4 tons on a busy day. The supplier usually takes 10 days; one delivery took 15. Keep the same time unit throughout: if you work in weeks, use weekly use and weeks of lead time.

The advanced method, one piece at a time

The simple method assumes your busiest day and your slowest delivery happen at the same time. That is rare, so it often keeps more than you need. The advanced method looks at how much your use and your deliveries actually swing, and sets the cushion for the level of protection you choose. The formula looks intimidating, but it is built from five numbers you can find in your own records.

The formula, color-coded
Safety stock=Z×√(L×σd²+d²×σL²)
dAverage daily use

What you normally use in a day

From your use history1.0 ton a day
σdDaily swing in use

How far a typical day lands above or below the average

The toolkit works it out0.36 ton
LAverage lead time

Days from placing an order to the goods arriving

Your last 10 or so deliveries10 days
σLSwing in lead time

How many days a typical delivery lands early or late

Your last 10 or so deliveries2 days
ZProtection level

How much cushion you choose: higher means fewer shortages and more stock

Pick from Figure 71.65, for 95%
σ (sigma) is the statistician’s symbol for swing, also called standard deviation.² means a number multiplied by itself: 2² = 2 × 2 = 4.√ is the square root, which undoes the ²: √4 = 2.
Putting it together for steel coil, in four steps
1
Cushion for swings in use

How much use could drift while you wait for a normal delivery

L × σd²
10 × (0.36 × 0.36) = 1.3
2
Cushion for late deliveries

What you would use in the extra days of a late delivery

d² × σL²
(1.0 × 1.0) × (2 × 2) = 4.0
3
Combine the two, back in tons

Add them, then take the square root

√(1 + 2)
√(1.3 + 4.0) = √5.3 = 2.3 tons
4
Choose your protection

Multiply by Z for the protection level you picked

Z × 3
1.65 × 2.3 = 3.8, about 4 tons
Figure 6. The advanced method, built step by step for steel coil
Z: how much protection do you want?
90%Z = 1.28May run short about 1 order cycle in 10
95%Z = 1.65About 1 in 20Most A items
98%Z = 2.05About 1 in 50Critical items
99%Z = 2.33About 1 in 100Critical items
An order cycle is the stretch from placing an order to the goods arriving. These percentages are not the share of customer orders shipped on time, which is usually higher, and they assume use and deliveries are fairly regular.
Figure 7. Choosing a protection level
Same item, two answers
Simple method
11 tons
Advanced method, 95%
4 tons

The simple method plans for the worst day and the worst delivery at once. The advanced method plans for how often they really happen. For steady items with reliable suppliers, the advanced answer is usually lower; for items that swing a lot, it can be higher.

Never switch an item just because the formula gives a smaller number. Move it in a pilot (section 07), once its records are accurate and you have a few months of daily or weekly use and about a dozen deliveries. Items ordered in lumpy, one-off batches do not suit the formula; base their cushion on customer forecasts instead.

06 · When and how much

Decide when to order and how much

Two decisions follow from safety stock: the reorder point tells you when to order, and the order quantity tells you how much. Both start from what you will really have, not just what is on the shelf.

On hand38 tons
+
On order0 tons
−
Promised to firm orders6 tons
=
Stock position32 tonsReorder point 26 tons
→
DecisionNo orderCheck again next week
Figure 8. Steel coil at this week’s check: order only when the stock position drops to the reorder point
Lead time: 10 days Order20 tons Maximum Reorder point Safety stock Order placed Days Tons on hand
Figure 9. Stock falls as you use it; an order goes out at the reorder point and arrives after the lead time
Checked every day

Reorder point = daily use × lead time + safety stock

Steel coil: 1.0 × 10 + 11 = 21 tons. Maximum: safety stock + one order = 31 tons.

Checked once a week

Reorder point = daily use × (lead time + days between checks) + safety stock

Steel coil, checked every 5 working days: 1.0 × 15 + 11 = 26 tons. Maximum: 36 tons.

If you check stock only once a week, an item can drop past its reorder point between checks and run short before the order arrives. Adding the days between checks covers that gap.

Work out an item’s safety stock and reorder point

Safety stock (simple method)11.0
Reorder point26.0
Use while you wait for the order15.0

In the item’s own unit, with use and lead time in the same time unit (days here; weeks work too). Filled in for steel coil, checked weekly. The toolkit also works out the advanced method.

Four stock numbers, used the same way in both stock guides
Safety stock
Average21 Reorder point26 Maximum36
010203040 tons
11 tonsSafety stock

The cushion for busy days and late deliveries

26 tonsReorder point

When your stock position drops to this, place an order

36 tonsMaximum

The most you should have, just after an order arrives

about 21 tonsAverage stock

Safety stock plus half an order: a guide to the cash tied up, not a limit

Steel coil, checked weekly. The companion guide measures idle stock against the maximum.

Order quantity: what you need, what the supplier sells, what makes sense

NeededUse between orders

Steel coil, ordered every two weeks: 10 tons.

vs
AllowedWhat the supplier sells

Minimum order, pack size, price breaks. Steel coil comes in lots of 20 tons.

→
Makes senseYour decision

Usually the larger of the two, rounded up to the pack size, unless the minimum is so big that holding it costs more than it saves. Steel coil: 20 tons.

How many months of use does the supplier’s minimum cover?
Your need or lessOrder what you need
Up to about 3 monthsOrder the minimum
Over 3 months, or it can expire or changeAsk for a smaller lot, a standing order delivered in parts, or another supplier
Over a yearGet the owner’s OK first
03 months12 months+
Figure 10. What to do with a supplier’s minimum; the 3- and 12-month lines are examples to adjust

Is the bigger order worth the discount?

Discount saved$1,800
Extra cost of holding it, and the risk$1,320
VerdictWorth it, narrowly

Aluminum extrusions. Both options buy 3,000 units over the six months the bigger order lasts. The bigger order also ties up about $22,800 more cash at the start. The chance the extra is never used is your best guess, from how long the product lasts, how sure the forecast is and past write-offs.

Starting rules for each group: examples to adapt
A items, low or medium swing
Safety stock
Simple method, then 95% in a pilot
Order size
2–4 weeks of use, or the minimum
Check
Weekly
A or B items, high swing
Safety stock
From the customer’s forecast
Order size
Matched to forecasts and firm orders
Check
Weekly
B items, and C items with low or medium swing
Safety stock
Simple method
Order size
1–3 months of use
Check
Monthly
C items, high swing
Safety stock
None or a few units, if not critical and the supplier is reliable
Order size
When a job needs it
Check
Monthly
Critical items
Safety stock
98% or 99%: your call
Order size
As for its group
Check
Weekly

Order sizes and how often you check are examples to adapt. The critical flag beats the group: a cheap part that can stop a line is planned as critical. Seasonal items use last year’s same month and build up ahead of the peak on a dated plan, then stop. Colors match Figure 3.

At each check, work out the order the same way every time: the gap between the stock position and the reorder point, plus what you will use until the next order, rounded up to the supplier’s pack size. If that would take the item above its maximum, ask for a smaller lot or a later delivery first, and get approval if neither is possible.

07 · Put it in place

Put the new levels in place safely

Compare each item’s stock with its new range, from safety stock up to the maximum. Some items will be above it and some below. Leave out stock promised to firm customer orders.

$950k
Stock today
−$150k
Too much of items you use; runs down
−$125k
Slow and obsolete; companion guide
−$12k
Stalled jobs
+$25k
Too little, including 2 critical items
$688k
Target, about 72 days
Figure 11. From stock today to target: some items need more, not less. Active work in progress stays at $118k
Safety rules for the pilot

About 20 items for about eight weeks

Lower in steps, for example a quarter at a time

Critical items keep their full cushion

Count shortages weekly, next to stock value

If shortages rise, the old level comes back

One planner signs off every change

Pick pilot items that matter but will not stop the line: A and B items with steady use, good records, a reliable supplier and enough history for the advanced method. Items without that history stay on the simple method until they have it. Agree when you will go back to the old level before you start, and write down each item’s shortages in the eight weeks before the pilot, so you know what normal looks like.

The weekly order check, about 20 minutes
Stock position

For each item: on hand + on order − promised

Reorder point

List the items at or below it

Changes

Customer, design or plan changes since last week

Quantity

Need vs supplier lot; above the maximum needs approval

Order

Place, move or reduce orders

Shortages

Any on pilot or critical items?

Week 1Check records and measure lead times for the top 20–30 itemsRecords you trust
Week 2Sort items; mark seasonal and critical onesGroups and flags
Week 3Choose how to estimate use; ask customers for forecastsUse estimates
Week 4Set levels with the simple method; start the weekly checkItem levels
Weeks 5–8Try the advanced method on items that have the recordsProof it is safe
ThenWeekly order check · Monthly estimate checks and counts · Quarterly re-sort items, reset levels and review supplier minimums and lead times
Figure 12. The first eight weeks, then the rhythm that keeps levels right

Name one planner to keep the item levels and run the weekly check, with a backup. Purchasing places and changes orders, sales brings customer forecasts and changes, production confirms the plan and the critical list, and the owner approves orders above the maximum and any change to a critical item’s cushion. In a small company these may be three people; what matters is that each job has a name.

Measures to track

ShortagesDown

Jobs or shipments delayed by a missing item

Days of stockDown

For materials, work in progress and finished goods

Items below safety stockDown

How many, with critical items listed by name

How far offDown

Estimate misses on A items, from section 04

Too high or too lowNear 0

The direction of the misses, from section 04

Count checkUp

Items matching the system ÷ items counted

08 · The toolkit

Let the toolkit do the math

Every calculation in this guide is already built into the free Stock toolkit. You fill in the yellow cells; the teal cells work themselves out. Start with the blue example rows to see how it works, then type over them with your own items.

You type inThe toolkit works outYou use it to
Tab 1Use and sort
Item and unitCost of one unit12 months of useCritical? Seasonal?
→
A, B or CSwing score and bandAverage daily use (d)Daily swing (σd)
Sort your itemsSections 02–03
Tab 2Item levels
Busiest day’s useUsual and longest lead time (L)Lead-time swing (σL)Days between checksSupplier lot sizeSimple or advanced
→
Safety stock, both methodsReorder pointMaximumAverage stock
Set each item’s levelsSections 05–06
Tab 3Weekly orders
On handOn orderPromised to firm ordersDays of use to cover
→
Stock positionOrder now? Yes or noQuantity, rounded to the lotWarning if above the maximum
Run the weekly order checkSections 06–07
Tabs 4–6Checks
Estimate and actual, A itemsTwo order sizes and the discountShortages, week by week
→
How far off, too high or too lowIs the bigger order worth it?Keep the new level or go back
Check and adjustSections 04, 06, 07
Yellow: fill inTeal: calculated for youBlue: example rows to type overThe rules, such as the 80/15/5 split and the protection levels, sit on the Start tab and can be changed in one place.
Figure 13. What goes into the toolkit and what comes out

09 · Working templates

Stock level templates

Stock toolkit (Excel)Every template in this section as a spreadsheet, each with a filled-in example. Type in 12 months of use and a few facts per item, and it sorts your items and works out safety stock, reorder points and order sizes.
Download

1. Item levels one row per item you keep; reset every quarter

ItemUnitA, B or CSwing scoreSeasonal?Critical?Daily useLead time: usual, longestHow often checkedSafety stockReorder pointOrder size or lotMaximum
Steel coiltonsA0.08NoNo1.010, 15 daysWeekly11262036

2. Weekly order check every item at or near its reorder point

ItemOn handOn orderPromised to firm ordersStock positionReorder pointOrder?Quantity, rounded to lotAbove maximum? Approved by
Steel coil38063226No––

3. Estimate check A items, monthly

MonthItemEstimateActualUnit costMiss, ignoring + or − ($)Estimate − actual ($)Why it missed, if by a lot

4. Pilot tracker about 20 items, weekly for eight weeks

ItemOld safety stockNew safety stockWeekShortages this weekShortages a week before the pilot (average)Stock valueKeep or go back

5. Monthly review

MonthDays of stock: materials, in production, finishedShortagesItems below safety stockHow far offToo high or too lowCount checkActions

6. What to say

WhenMessage
Smaller minimum“We use about [quantity] of [item] a month. Could you supply it in lots of [quantity], or set up a blanket order with monthly releases?”
Lead time“Over the last [number] deliveries your lead time on [item] ranged from [days] to [days]. What would it take to make it reliably [days]?”
Reschedule an order“Our plan for [item] has changed. Could we move PO [number] from [date] to [date], with no change to price?”
Customer forecast“To keep your lead times short, could you share a rough forecast of your orders for the next three months? We update our plan each month.”
Seasonal build“We plan to build stock of [item] for your [season] peak. Could you confirm your expected volumes by [date], so we buy materials once and not twice?”